Home > NPPs in Japan > Hamaoka-3
NPPs in Japan
Outage since 2010-11-29
Hamaoka-3
| Age: |
38 |
| Reactor Type: |
BWR |
| Gross Output: |
1100MWe |
| Net Output: |
1056MWe |
| Owner: |
Chubu EPCO |
| Operator: |
Chubu EPCO |
| Applications for Restart: |
2015-06-16 |
| Date of order: |
1982 |
| Construction Start: |
1982-11 |
| Concrete placing: |
1983-04-18 |
| Initial Criticality: |
1986-11-21 |
| Grid connection: |
1987-01-20 |
| Commercial Operation: |
1987-08-28 |
| Main contractor: |
Toshiba/Hitachi |
| Architect Engineer: |
Toshiba/Hitachi |
| Reactor System supplier: |
Toshiba |
| Reactor Vessel supplier: |
Toshiba/IHI |
| Incore Structure supplier: |
Toshiba |
| Fuel supplier: |
GNF-J/NFI |
| Steam raising supplier: |
Hitachi |
| Turbine generator supplier: |
Hitachi |
| Civil works: |
various |