Home > NPPs in Japan > Tokai-1
NPPs in Japan
Under decommissioning
Tokai-1
| Age: |
31 |
| Reactor Type: |
GCR |
| Gross Output: |
166MWe |
| Net Output: |
159MWe |
| Owner: |
JAPC |
| Operator: |
JAPC |
| Date of order: |
1959 |
| Construction Start: |
1960-01 |
| Concrete placing: |
1961-03 |
| Initial Criticality: |
1965-05-04 |
| Grid connection: |
1965-11-10 |
| Commercial Operation: |
1966-07-25 |
| Main contractor: |
GEC/SC |
| Architect Engineer: |
GEC |
| Reactor System supplier: |
GEC |
| Reactor Vessel supplier: |
Fuji |
| Incore Structure supplier: |
Fuji |
| Fuel supplier: |
BNFL |
| Steam raising supplier: |
KHI |
| Turbine generator supplier: |
GEC |
| Civil works: |
Shimizu/Kajima |