Home > NPPs in Japan > Tokai-2
NPPs in Japan
Outage since 2011-03-11
Tokai-2
| Age: |
46 |
| Reactor Type: |
BWR |
| Gross Output: |
1100MWe |
| Net Output: |
1056MWe |
| Owner: |
JAPC |
| Operator: |
JAPC |
| Applications for Restart: |
2014-05-20 |
| NRA's Approval for basic design: |
2018-09-26 |
| NRA's Approval for detailed design: |
2018-10-18 |
| Date of order: |
1971 |
| Construction Start: |
1973-06 |
| Concrete placing: |
1973-10 |
| Initial Criticality: |
1978-1-18 |
| Grid connection: |
1978-3-13 |
| Commercial Operation: |
1978-11-28 |
| Main contractor: |
GE/Hitachi/Shimizu |
| Architect Engineer: |
EBASCO |
| Reactor System supplier: |
GE |
| Reactor Vessel supplier: |
GE |
| Incore Structure supplier: |
GE |
| Fuel supplier: |
GE/NFI |
| Steam raising supplier: |
GE |
| Turbine generator supplier: |
GE |
| Civil works: |
Shimizu/Kajima |