- 2 February, 2018 Capacity Factor of Sendai-1 Last Year Was 106.7%
- 13 February, 2017 Kagoshima Experts’ Committee Confirms Sendai-1 Inspection Results
- 10 January, 2017 Sendai-1 NPP Shifts to Commercial Operation
- 9 December, 2016 Sendai-1 Restarted: Kagoshima Governor Effectively Accepts
- 15 November, 2016 Kagoshima Governor Visits Reactor, Shows Some Appreciation for Special Inspections by Kyushu Electric Power
- 12 September, 2016 Kagoshima Governor Reiterates Demand to Have Sendai Reactors Suspended
- 31 August, 2016 Kagoshima Governor Asks for Temporary Suspension of Operation of Sendai NPPs
- 12 July, 2016 Kagoshima Governor Election: Rookie Claims Victory, Pledging Temporary Shutdown of Sendai Reactors
- 6 April, 2016 Request Denied for Order Prohibiting Operation of Sendai NPPs: “New Regulatory Standards Are Rational”
- 17 August, 2015 Industrial Groups Welcome Sendai-1 Startup as Major Step toward Restarting Japan’s Other Reactors
- 11 August, 2015 Kyushu Electric Power Starts Up Sendai-1, Ending 23-month Hiatus in Japanese NPP Operation
- 28 May, 2015 NRA Completes Examination of Sendai Reactors, Allowing Unit 1 to Restart by July 31
- 23 April, 2015 Kagoshima District Court Rejects Request for Order Prohibiting Restart of Sendai-1 and -2 NPPs
- 3 April, 2015 Pre-Service Inspection Starts at Sendai-1 before Restart
- 6 February, 2015 Kagoshima Governor Comments on Slow Restart of Sendai NPS